## Overview

The **DATE\_OFFSET** function **offsets a time level value forward or backward by a number of years, quarters, months, weeks, or days.**

Use this function in dynamic project variables when one time level value should always be derived from another rather than entered manually (for example, the forecast end from the forecast start).

## Syntax

`DATE_OFFSET("TimeLevelValue", "TimeLevel", Offset)`

**Example usage:** `DATE_OFFSET("$FORECAST_START", "Month", 12)`

## Parameters

| Parameter          | Description                                                                                                                                                      | Type        | Required |
| ------------------ | ---------------------------------------------------------------------------------------------------------------------------------------------------------------- | ----------- | -------- |
| **TimeLevelValue** | A value of any time level in the project's time dimension, given as a quoted string or as a variable reference (for example `"2026-01"` or `"$FORECAST_START"`). | Level value | Yes      |
| **TimeLevel**      | The time level on which to offset. Allowed values: `"Year"`, `"Quarter"`, `"Month"`, `"Week"`, `"Day"`.                                                          | Level name  | Yes      |
| **Offset**         | The number of TimeLevel steps to offset by.                                                                                                                      | Integer     | Yes      |

## Output shape

| Aspect      | Behavior                                |
| ----------- | --------------------------------------- |
| Return type | Level value                             |
| Format      | Same format as the input TimeLevelValue |

## Watch out

* Both `TimeLevelValue` and the resulting value must be valid level values within the [project's time horizon](/changing-the-time-horizon/).
* `Offset` can be negative: positive values offset forward in time, negative values offset backward.
* When the level on which you offset is smaller than your input's level, the offset starts from the first day of your input. The result is always returned at your input's level. See the "Offset a quarter by months" example below.
* Only time-dimension levels are accepted. Other dimensions cannot be passed here.

## Examples

### Add one year

**Formula:** `DATE_OFFSET("2026", "Year", 1)`

| TimeLevelValue | TimeLevel | Offset | DATE\_OFFSET Result |
| -------------- | --------- | ------ | ------------------- |
| `"2026"`       | `"Year"`  | `1`    | `"2027"`            |

### Subtract one day

**Formula:** `DATE_OFFSET("20260101", "Day", -1)`

| TimeLevelValue | TimeLevel | Offset | DATE\_OFFSET Result |
| -------------- | --------- | ------ | ------------------- |
| `"20260101"`   | `"Day"`   | `-1`   | `"20251231"`        |

### Derive a forecast end from a forecast start

If a project has a fixed variable `$FORECAST_START = "2026-04"`, you can define a derived variable `FORECAST_END` as:

**Formula:** `DATE_OFFSET("$FORECAST_START", "Month", 12)`

| TimeLevelValue | DATE\_OFFSET Result |
| -------------- | ------------------- |
| `"2026-04"`    | `"2027-04"`         |

The derived variable updates automatically whenever `$FORECAST_START` is changed.

### Derive last actuals from forecast start

A common pattern: the last actuals month is one month before the forecast start.

**Formula:** `DATE_OFFSET("$FORECAST_START", "Month", -1)`

| TimeLevelValue | DATE\_OFFSET Result |
| -------------- | ------------------- |
| `"2026-04"`    | `"2026-03"`         |

### Offset a quarter by months

`"2026-Q3"` is treated as July 1 (the first day of Q3). The offset moves from that date, and the result is given back as a quarter.

| Formula                               | DATE\_OFFSET Result | Why                                                    |
| ------------------------------------- | ------------------- | ------------------------------------------------------ |
| `DATE_OFFSET("2026-Q3", "Month", 1)`  | `"2026-Q3"`         | July 1 + 1 month = August 1, which is in Q3            |
| `DATE_OFFSET("2026-Q3", "Month", -1)` | `"2026-Q2"`         | July 1 - 1 month = June 1, which is in Q2              |
| `DATE_OFFSET("2026-Q3", "Year", -1)`  | `"2025-Q3"`         | July 1 - 1 year = July 1, 2025, which is in Q3 of 2025 |

### Derive the planning year from the forecast start

To compute the year after the forecast start's year, use [DATE\_EXTRACT](/date-extract/) to drop down to the Year level first, then offset by one year.

If `$FORECAST_START = "2026-04"`:

**Formula:** `DATE_OFFSET(DATE_EXTRACT("$FORECAST_START", "Year"), "Year", 1)`

| Step                                      | Result   |
| ----------------------------------------- | -------- |
| `DATE_EXTRACT("$FORECAST_START", "Year")` | `"2026"` |
| `DATE_OFFSET("2026", "Year", 1)`          | `"2027"` |

The combined result is `"2027"`.